Project | Commissioning Year | Location | Annual Production | Total reactor capacity | Biomass input |
---|---|---|---|---|---|
Grauballegård Biogasanlæg ApS | 2021 | Lemming, Denmark | 6,000,000 Nm³ biomethane | 90,000 t/year | |
Vesthimmerland Biogas A/S | 2020 | Farsø, Denmark | 25,500,000 Nm³ biomethane | 44,000 m³ | 265,000 t/year |
Vinkel Bioenergi A/S | 2019 | Højslev, Denmark | 52,000,000 Nm³ biomethane | 72,300 m³ | 430,000 t/year |
Outrup Biogas ApS | 2019 | Outrup, Denmark | 8,000,000 Nm³ biomethane | 32,600 m³ | 125,000 t/year |
Storde Biogas I/S | 2018 | Bredebro, Denmark | 6,500,000 Nm³ biomethane | 18,000 m³ | 100,000 t/year |
Ringsted Biogas ApS | 2018 | Ringsted, Denmark | 6,100,000 Nm³ biomethane | 13,800 m³ | 40,000 t/year |
Hærup Biogas ApS | 2018 | Klejtrup, Denmark | 2,200,000 Nm³ biomethane | 6,000 m³ | 40,000 t/year |
Iglsø Biogas A/S | 2018 | Stoholm, Denmark | 6,800,000 Nm³ biometan | 21,500 m³ | 150,000 t/year |
Vestjysk Biogas ApS | 2017 | Borris, Denmark | 5,000,000 Nm³ biomethane | 18,500 m³ | 80,000 t/year |
Grønhøj Bioenergi A/S | 2017 | Grønhøj, Denmark | 7,000,000 Nm³ biomethane | 21,500 m³ | 130,000 t/year |
Lykkeslund Bioenergi ApS | 2017 | Otterup, Denmark | 4,000,000 Nm³ biomethane | 8,600 m³ | 36,000 t/year |
Zastrow Bioenergi ApS | 2016 | Otterup, Denmark | 3,000,000 Nm³ biomethane | 8,600 m³ | |
Vrejlev Bioenergi P/S | 2016 | Vrå, Denmark | 3,400,000 Nm³ biomethane | 100,000 t/year | |
Viftrup Biogas P/S | 2015 | Spjald, Denmark | 2,400,000 Nm³ biomethane | 8,600 m³ | 70,000 t/year |
OL Biogas ApS | 2015 | Hadsten, Denmark | 5,000,000 Nm³ biomethane | 50,000 t/year | |
Madsen Bioenergi I/S | 2014 | Balling, Denmark | 5,000,000 Nm³ biomethane | 27,600 m³ | 130,000 t/year |
Holbæk Bioenergi I/S | Skærbæk, Denmark | 1,700,000 Nm³ biomethane | 50,000 t/year | ||
Michael Sangild | 2014 | Søndersø, Denmark | 21,500 m³ | ||
Niels Keldsen | 2014 | Skals, Denmark | 0.8 mW electricity – heat | 7,800 m³ | |
S. & H. Roe | 2014 | Lincoln, Great Britain | 4.2 mW electricity – heat | 7,000 m³ | |
Wapnö Gods Biogasanlæg | 2012 | Halmstad, Sweden | 3 mW electricity – heat/cooling | 3,000 m³ | 40,000 t/year |
Beeswax Farming | 2010 | Lincoln, Great Britain | 4.2 mW electricity – heat | 7,000 m³ | |
Anders Rosenkvist | 2010 | Skærbæk, Denmark | 1 mW electricity – 1,500,000 Nm³ biomethane | 6,000 m³ | |
Bjarne Viller Hansen | 2009 | Bording, Denmark | 3 mW electricity – heat | 3,000 m³ | |
Niels Lund | 2008 | Wanderup, Germany | 4 mW electricity – heat | 3,000 m³ | |
Ejnar Kirk | 2007 | Skinnerup, Denmark | 2.8 mW electricity – heat | 4,000 m3 | |
Jens Kirk | 2007 | Skinnerup, Denmark | 3 mW electricity – heat | 3,000 m3 | |
Bent Pedersen | 2007 | Rødkærsbro, Denmark | 3.3 mW electricity – heat | 3,000 m3 | |
Søren Riis | 2007 | Bedsted, Denmark | 570 m3 | ||
Michael Sangild | 2006 | Rødekro, Denmark | 6,000 m3 | ||
Bio-Tec A/S | 2006 | Telemarken, Norway | 3,000 m3 | ||
Tom Larsen | 2006 | Gedsted, Denmark | 3,000 m3 | ||
Urban Biogas | 2006 | Wünstig, Germany | 5.4 mW – heat | 2,000 m3 | |
Ole Kappel | 2006 | Hurup, Denmark | |||
Bio-Tec A/S | 2005 | Jevnaker, Norway |